Completion of a new town hall in Lamia (Old Hospital) | |
CONSTRUCTION | ZISIMOPOULOS BROS SA |
STUDY / SUPERVISION | TECHNICAL SERVICE OF LAMIA MUNICIPALITY |
STUDY BUDGET | 1.093.495,94€ |
YEAR OF CONSTRUCTION | 2017-2018 |
This is a transformation of the former hospital of Lamia into a new City Hall. The project concerned the complete conversion and renovation of the 2nd and 3rd floor as well as the basement and the boiler room building, a total of over 2,000m2..
The renovation included static restorations and reinforcements of the load-bearing structure of the building, new interior arrangements, complete change of all electromechanical installations (heating, cooling, air conditioning, water supply, sewerage, strong and weak currents), addition of a new external elevator.
Replacement of all building finishes (floors, suspended ceilings, partitions, etc.) by maintaining only the frame of the building and the external masonry. The insulation of the building was also completely replaced.